As mentioned in the previous episode, the clean room project start to built on 28th April 2022 and customers already finished the cleanroom walls installation.
The project start to built on 28th April 2022. Before the start of the project, as usual, we introduced the installation tools required for the clean room to the customer, as well as the function and usage of each part of the accessories. After the guidance of our engineers, the customer gradually recognized the name of eachpart of the product. The client's engineers produced a rough outline of the cleanroom in just three days. According to our installation drawings and videos, the engineers ins
The changing room total area is 30 square meter, length by width 7.5*4 meter.It's designed for a spaghetti packing workshop.The ceiling panel through the screw rod hoisted to the roof of the workshop
Welcome call us or please submit your inquiry via the form so that we can provide you the best possible customer service.
We have more than 17 years of experience in cleanroom turnkey projects , with business all over the world. We adhere to the principle of customer first, serve every cooperative customer attentively, and focus on the standard delivery of each cleanroom project.
Dear, I will reply in 12 hours. All your message are protected!
Address: NO.188 xiangwei road, near junction of xiangwei road and chengyang road (the second floor of south building inside of haiji feiyue) Xiangcheng district, Suzhou city, Jiangsu province, China