As mentioned in the previous episode, the clean room project start to built on 28th April 2022 and customers already finished the cleanroom walls installation.
In early May 2022, the customers started the construction of the clean room ceiling and quick start of HVAC(Heating Ventilation and Air Conditioning) system in Mid-May .
Cleanrooms operate under very strict internal air conditions that require HVAC systems to not only provide close-band temperature limits,but also humidity control and very high efficiency filtration.
The HVAC systems are to delivery air change rates that are far in excess of normal atmospheric conditions & ensure a low particle count for applications such as high quality product manufacture or scientific and medical research.
Each part of our material is marked with a corresponding number, which can easily correspond to the installation drawing,ensure customers can find accessories in the shortest time and connect easily, ensuring efficiency and accuracy .