Construction Sequence for Cleanroom Plant Projects

1. Cleanroom Construction Requirements
1.1 General Principles
Cleanrooms must be constructed in accordance with the design drawings. Any modifications required during construction shall be supported by a modification notice issued by the design unit. Before cleanroom construction begins, a detailed construction plan and procedure shall be prepared. During construction, all trades shall coordinate closely and proceed according to the approved sequence. Work performed earlier shall not obstruct subsequent construction activities.
All materials, equipment, finished products, and semi-finished products used in the project shall comply with the design requirements and shall be accompanied by factory certificates of conformity or quality certification documents. During cleanroom construction, intermediate inspection and acceptance shall be carried out after each construction step is completed, and records shall be maintained.
1.2 General Provisions
Cleanroom architectural decoration works shall commence only after the roof waterproofing works and external envelope structure have been completed, external doors and windows have been installed, and the main structural acceptance has been carried out. The scope includes interior decoration works, door and window installation, gap sealing, and sealing at junctions between various pipelines, lighting fixtures, purified air-conditioning equipment, process equipment, and the building structure.
The construction schedule for cleanroom architectural decoration shall be coordinated with other specialized trades through a clear construction cooperation plan. Construction shall proceed in sequence, with mutual coordination among all parties.
In addition to compliance with applicable national standards, cleanroom architectural decoration construction shall ensure airtightness, minimize dust generation during construction, and maintain cleanliness at the construction site. The ambient temperature at the cleanroom decoration construction site shall not be lower than 10°C. For special decoration works, construction shall be carried out in accordance with the relevant product instructions.
1.3 Material Requirements
Elastic sealing materials and dust-proof coatings used for joint sealing in cleanrooms shall be accompanied by documentation indicating their composition, type, date of manufacture, storage validity period, application instructions, and product qualification certificates. Expired products and products that have not been properly evaluated shall not be used.
The cement grade for the cement mortar base of cleanroom coated floors shall not be lower than Grade 425. The moisture content of wood used on cleanroom walls shall not exceed 16%, and wood shall not be left exposed. Gypsum boards, plywood, and wooden keels shall be treated for moisture protection, or waterproof gypsum boards shall be used. Wood and gypsum boards shall not be used as surface decoration materials in biological cleanrooms.
1.4 Structural and Decoration Requirements
Embedded iron components, wooden frames, and similar items in reinforced concrete members and walls shall be securely fixed. Wooden blocks and wooden frames shall be treated for corrosion protection. Exposed parts of embedded iron components, as well as suspension rods and supports, shall be treated for rust prevention or corrosion protection.
All architectural components, partition walls, ceiling fixings, and suspension members shall be connected to the main structural system. They shall not be connected to equipment supports, such as conveyor suspension rods, air duct suspension rods, or supports for vibrating equipment, nor to pipeline supports.
Gaps in architectural finishes and around doors and windows shall be sealed on the positive-pressure side. After renovation works involving partition removal, opening formation, and penetration of pipelines through walls or floor slabs, the affected areas shall be properly repaired and finished to prevent dust accumulation and falling debris.
Concealed pipeline works shall be accepted only after pipeline installation and pressure testing have been completed. Openings around pipeline penetrations through walls and ceilings shall be repaired to a flat, tight, and clean condition, and sealed with appropriate sealing materials. Airtight sealing gaskets shall be applied around inspection openings for concealed works.
A waterproof membrane with a thickness of 0.4–0.6 mm shall be laid beneath the cleanroom floor screed as a moisture barrier. Joints shall overlap by at least 50 mm and be securely taped. Concrete pouring division lines should not pass through the cleanroom area. The moisture content of substrates for sheet and coating floor finishes shall not exceed 6–8%.
Skirting shall be flush with the wall surface or slightly recessed by 2–3 mm. Where the skirting and floor are made of the same material, a small coved corner may be formed, with a coving radius R not less than 50 mm. Where the skirting and floor materials differ, elastic sealing materials shall be used at the junction.
1.5 Construction Requirements
Architectural decoration works shall follow a strict construction sequence coordinated with all specialized trades. The typical sequence is as follows: opening formation and base preparation; installation of various specialized systems; internal door and window installation; repair of openings and surrounding areas; base layer preparation; plastering and cover panel works; joint sealing; painting and coating works; and wallpapering or lining works.
During cleanroom architectural decoration construction, dust shall be removed continuously. Cleaning records shall be maintained for concealed spaces, such as ceiling voids and cavity walls. Completed decoration surfaces shall be protected and shall not be damaged by impact, knocking, trampling, or excessive wet work, which may cause panel indentation, hidden cracking, or surface contamination.
No dust-generating activities shall be carried out in rooms where HEPA filters have already been installed.
Before installing plastic sheet or rolled floor finishes, materials shall be pre-classified by size and thickness. Adhesive shall be fully applied between the sheets or rolls and the floor. The surface shall be smoothed to eliminate air pockets, with no missed areas or trapped air.
Before sealant is applied, debris and oil shall be completely removed from the joint grooves, and the surfaces shall be kept dry. Temporary equipment openings in the cleanroom shall be closed when not in use to prevent ingress of dust and debris. The construction site shall maintain adequate ventilation and lighting.
For renovation projects, existing power supplies and pipelines carrying flammable, explosive, or toxic gases shall be identified and isolated before construction begins. Appropriate safety measures shall be implemented for corrosive liquids used in process operations.
1.6 Installation of Prefabricated / Modular Cleanrooms
Prefabricated or modular cleanrooms shall be installed indoors after the architectural decoration works have been completed. The interior space shall be clean and free of accumulated dust. Components and the installation area shall be cleaned and wiped continuously during construction and installation.
During installation, fixing points such as suspension members and anchor fasteners shall first be secured to the main structure, floor slabs, and floor surfaces. The finished floor surface shall be flat, with unevenness not exceeding 0.1%. When installing rolled or coated floor finishes, sealing at junctions with vertical wall panels shall be properly considered.
Before wall panel installation, accurate setting-out shall be carried out. Corner joints shall be vertically aligned to prevent cumulative errors that may cause panel misalignment or distortion. The verticality deviation of wall panels shall not exceed 0.2%.
Ceilings shall be cambered across the room width so that they remain flat under service loading. The ceiling perimeter shall be tightly sealed against the walls. Protective films on panel surfaces shall not be removed during installation, and panels shall not be struck or stepped on.
All components and materials shall be stored in a clean, dry, enclosed environment and placed flat on moisture-proof membranes. Unpacking and opening of components shall be carried out in a clean environment. Specifications, performance, and condition shall be strictly inspected. Non-conforming or damaged components shall not be installed.
Surfaces to which facing materials are bonded, sealant-filled joints, and grooves shall be thoroughly cleaned to remove debris and oil, ensuring firm adhesion and preventing detachment or dust accumulation. All installation gaps in prefabricated or modular cleanrooms shall be sealed with sealant.
Suzhou Pharma Machinery Co.,Ltd.
2026/11/27
Gino

prev
Causes and Preventive Measures for Air Conditioner Condensate Water
Get in touch with us
Address: NO.188 xiangwei road, near junction of xiangwei road and chengyang road (the second floor of south building inside of haiji feiyue) Xiangcheng district, Suzhou city, Jiangsu province, China
Copyright © 2026 Suzhou Pharma Machinery Co., Ltd. | Privacy Policy  Sitemap
Contact us
email
whatsapp
Contact customer service
Contact us
email
whatsapp
cancel
Customer service